How do you determine a project timescale?
The timescale of a project is dependent on many factors. It could
be that the producer is working to a delivery date specified by
the client for transmission or to coincide with a campaign or event.
If this is the case then it is sensible practice to use the delivery
date as the starting point for the schedule and work backwards to
allocate your time effectively. When do you draw
up a schedule?
A schedule should be drawn up very early on in the production process
as it has many functions.
- Determines production achievability in terms of timescale
and budget
- Keeps the client and team informed of exactly what is happening
at any time
- Serves as a detailed summary of the entire production process
- Helps to determine crew and format requirements
- Acts as a reminder list so that nothing is forgotten
Whatever the circumstances, projects generally need to have
a definite end point. Whether you're working in television, multimedia
or graphic design, the commissioner / client needs to be able
to produce a product to a certain specification for a specific
time in order to make money and survive. However, it is sometimes
difficult to allocate a set time for the creative process without
it being too much of a constraint.
 |
Obviously the creative process is the
one that's always more difficult for people to establish,
but it's crucial that people do. In the design industries
people keep that open-ended far too often.
Grant Campbell |
 |
|
What should a schedule contain?
- Detailed information about what is going on throughout the
whole production process
- Detailed information about roles and responsibilities for
the duration
- Indication of the various project sign off stages
What else should a schedule take into consideration?
- It should remain consistent with agreed start and end dates
and allow for testing
- Additional time must always be included to provide leeway
for the unexpected
- If a project is budgeted on a very tight timescale then problems
may arise further down the line with possible over-running
The production phase
Once a production is underway it is important to keep accurate
records and ensure that the following occurs:
- Monitor and record all the time spent on the project
- Ensure good communication between the client and producer
and ensure the client is updated at every phase
- Notify the client of sign off stages and when the cut off
points for any changes are reached
- Clients may change their minds during a project but they
should be informed that this may well affect the overall timescale
and can produce knock on effects in terms of budget and delivery
dates
- All companies work differently and the flexibility of a project's
timescale depends on the relationship that you have with a client
or broadcaster
- With any project, both the producer and the client's reputations
are at stake, so it is important to ensure that even if the
timescale is tight, the quality of the end product will not
suffer
 |
The schedule is normally put together
in a firm sense once we have a commission, so all we
do at the brief stage is make sure that we can do it
in a broad brush strokes way. Once you have a commission
you start scheduling exactly who is needed and it's
normally the production manager working with the executive
producer and liaising with the channel at the same time
because obviously we need to agree any staffing with
them and keep to budget. David Flynn |
 |
|
- If a project runs into difficulties along the way that have
not been accounted for negotiation may be required
- Delays may be circumstantial and not the fault of the client
or the producer, so circumstances dictate who should bear any
additional expenses
Making the most of your time
A well-constructed schedule makes the most effective use of your
time. It is then possible to be flexible within that. If you have
organised an exterior shoot on a particular day and it is raining,
alternatives should have been scheduled in so that days can be
swapped without losing valuable production time and wasting money.
In broadcast television, companies such as Endemol
may be working to the deadlines of commissioning editors and they
have to plan and assess carefully whether programme production
is realistically possible within the allocated timescale. Format
shows are sometimes easier to schedule because they follow the
same pattern as those previously produced, so experience can play
a huge part in allocating time.
Will there always be a written schedule?
There are occasions when there may not be a written schedule,
such as when working to immediate deadlines. Graphics can be required
for organisations such as GMTV
at extremely short notice so the brief will be verbal and the
production process will begin immediately in order to meet the
transmission deadline. Rendering or play out time must also be
taken into consideration when planning a timescale, as should
other equipment requirements.
In magazine publishing (www.futurenet.co.uk)
deadlines are everything and there is no leeway at all or the
end product will not be on the shelves by the target date. There
isn't always a written schedule but everybody is aware of time
constraints and their own responsibilities. Time needs to be allocated
and managed effectively as it can make the difference between
the success or failure of any project.
 |
We have about three and a half weeks to
produce a magazine from beginning to end and that's
all the shooting, all the photography, writing, designing,
sending it, creating it, making sure we're all happy
with it, getting it to the printers. There's no leeway
and if you miss the deadline, you're paying money to
get the magazine done. People will come down on you
really hard, so that's set in stone. We know the size
of the job we have to do so we have to go out and do
it. Mike Ellott |
 |
|
|